Precautions
This topic provides a brief overview of the general configuration process for data migration. The configuration varies slightly for different migration types. For more information on configuration steps, see Data Migration - Create Task.
Operation Steps
1. Go to the task list page of data migration.
2. Click Create Task to go to the migration task configuration page.
3. After filling in the task parameters and source and target database information, click Test Connection on the source and target databases.
4. After the connection test is passed, click Next: Select Objects to Migrate and check tables to migrate.
5. Select the tables to migrate and click Advanced Configuration to configure the table objects.